City of Suffolk & Isle of Wight County
MLRA: T-153A
HUC: 020802-08
This large watershed covers 161,365 acres. Originally, the critical area (about 66,000 acres) was defined as any farm within a one-mile radius of the tidal shellfish area, the reservoirs, or their principal tributaries. In 1985, the critical area was expanded to include 116,710 acres, of which 23,908 acres were cropped.
Participation by area farmers in the project was excellent. There was only enough money to fund 107 of the 132 applications filed. Farms were prioritized for contracting purposes. One hundred and ninety farms were represented by the 107 signed contracts. This represented approximately 78% of the 245 farms (15,034 acres) needing conservation treatments. An estimated 56,546 tons per year or 65% of the manure was treated.
Twelve categories of best management practices (BMPs) were utilized for control of sediment, nutrient, and pesticide losses or for manure storage and utilization. Pesticide and nitrogen management were two of the most widely used BMPs.
An initial baseline for water quality was established, followed by monthly and quarterly samples to detect water quality trends. Lack of funds caused the cancellation of the proposed final monitoring effort. There was no direct monitoring of land treatment to determine the effects of BMPs on water quality.
In spite of the high level of farmer participation and the number of acres treated, there was no improvement in water quality for the variables measured.
This project was characterized by an extremely high level of coordination and cooperation among the different agencies and a high level of participation among area farmers. The BMPs were selected properly. The inability of the project team to document water quality improvements attributable to land treatment is at least partially due to lack of funding for intense end-of-project monitoring. In addition, the size of the critical area was large and the number of applied BMPs was limited by funding which, most probably, decreased the overall effectiveness of BMPs on basin-wide water quality .
Figure 4.25: Nansemond - Chuckatuck (Virginia) RCWP project map, VA-1.
Water quality monitoring goals outlined the steps necessary for a coherent water quality monitoring plan.
Specific water quality variables utilized in goal setting must be monitored; otherwise, the goal is useless.
The Local Coordinating Committee (LCC) formed a very cohesive working group with no turf battles. There were four subcommittees: Administration, Information and Education (I&E), Technical Assistance, and Monitoring. There was a high degree of coordination among several agencies concerned with water quality monitoring. These included the utilities departments of the cities of Portsmouth and Norfolk, the Virginia Institute of Marine Sciences, the State Water Control Board, the State Department of Health, and the Hampton Roads Water Quality Agency, which was responsible for coordinating the monitoring program from 1981 through 1989. Beginning in 1990, the monitoring was coordinated by the Hampton Roads Planning District Commission (formerly the Southeastern Virginia Planning District Commission) (Spooner, 1991).
Several years before the project ended a number of agency personnel retired. The LCC and the State Coordinating Committee (SCC) discontinued their meetings. As a consequence of personnel changes and lack of meetings, communication broke down toward the end of the project.
Meetings must be continued through the life of the project in order to keep people informed, involved, and enthusiastic about the project.
Good coordination and communication among participating agencies is a necessary condition for a successful project. Other factors such as critical area or BMP selection are equally important in determining success.
The most effective tool the I&E committee had for communicating information to area farmers was one-to-one contact. The least effective tool was mailings.
CES was responsible for educating the farmers on fertilizer, animal waste, and pesticide management BMPs. Of the three, animal waste management was the most demanding because of the necessity for determining manure nutrient content, appropriate application rates, and type of application.
There is no substitute for one-to-one contacts to transfer technical information to the farmers. Through such contacts, staff can communicate the projects' goals and objectives directly to the farmer.
Some project personnel believed that in order for BMPs to have been effective in reducing nonpoint source (NPS) pollution, the entire watershed should have been designated as the critical area.
Several participants believed that Integrated Crop Management (ICM) would have been an extremely valuable BMP in that it would have dealt with the water quality problem within the context of a complete system rather than in separate parts.
Land treatment implementation practices were tracked through the use of color-coded SCS contracts. Annual status reviews were conducted by the SCS.
Farming practices that save the farmers money and are easily maintained will be continued beyond the formal end of the project.
Regression equations for the 1983-1988 water quality data were calculated using a program in STORET, but the equations have not been tested for significance. Improving trends in total suspended solids (TSS) and orthophosphorus (OP) was observed for Nansemond River as compared with reports from the 1960s. An improving trend in nitrate nitrogen (NO3-N) was observed for Chuckatuck Creek. However, these trends may not be attributable to the Rural Clean Water Program (RCWP) project because they emerged in the late 1960s after point sources were removed from the project area. Thus an improving trend in water quality was already in effect in the estuaries when the RCWP project began.
Analysis of water supply lakes in the project area indicates high variability in water quality data and little evidence of trends. Manipulation of the water supply lakes for water withdrawal and storage of pumped ground water substantially confounds results. Ground water with high OP contents was pumped into the reservoirs when the reservoirs drop below a specified height. No allowance was made for climatological variation, for events outside the project area such as a lack of homogeneity and changes in land use such as urbanization and population growth at the expense of farms and wetlands. No pesticide monitoring, flow measurements, or storm sampling was conducted.
Intense end of project water quality monitoring and statistical analysis had been planned. However, due to a shortage of funds, this monitoring and analysis was not completed.
Trend detection in reservoirs is difficult even under good conditions. When water quality measures are confounded by pumping ground water into a reservoir or drawing a reservoir down, trend detection is almost impossible. In order to determine the effectiveness of BMPs on water quality, tributaries should have been monitored using paired watershed or downstream/upstream monitoring.
1981 - 1991
Streams: 195 miles
2 estuaries: size not reported
Geologic Factors: The project area is characterized by nearly level to gently rolling topography with steep slopes adjacent to small tributary streams. Most soils have moderately low erodibility factors. Depth to ground water is generally 25 feet or more.
Use % of Project Area % of Critical Area Cropland 27 32 Pasture-range 3 NA Woodland 63 NA Urban/roads 1 NA Other Wetland 4 NA Unspecified 2 NA
Operation # Farms Total # Total Animals Units Animal Dairy 1 125 175 Beef 24 2,724 2,724 Hog 40 24,000 9,600 Poultry 8 448,000 1,478Animal numbers and annual production of manure decreased during the life of the project. From 1982 to 1984, dairy cow numbers declined by 275; hog numbers declined by 6,365. Poultry declined by 18,000 birds. This translates into a reduction of 13,381 tons or 13% of wet manure generated per year. Figures given above are for 1984.
SOURCES Federal State Farmer Other ACTIVITY SUM Cost Share 1,721,000 0 4,242,000 0 5,963,000 Info. & Ed. 63,900 0 0 2,000 65,900 Tech. Asst. 448,595 0 0 48,000 496,595 Water Quality Monitoring 72,000 23,400 0 25,000* 120,400 SUM 2,305,495 23,400 4,242,000 75,000 $6,645,895*** Additional funding for water quality monitoring (exact amounts unknown) was contributed by the following state and local agencies:
Source: Smolen et al., 1989
Teach farmers about nutrient management
Personal visits
Media coverage (newspapers, radio spots)
Meetings
Tours
Education materials
Diagnostic clinic
Farm demonstrations on the use of swine and broiler waste as a source of nitrogen
Soil and animal waste testing
Payment limit of $50,000 per contract (some contracts cover multiple tracts)
Excellent coordination among all the agencies involved, resulting in a well designed program that interested the farmers
Concern among area farmers that they would be regulated if they didn't participate
Lack of interest on the part of absentee landowners
Most structural BMPs and stabilizing structures at field edges will probably be maintained. Waterways will be harder to maintain due to the sandy soils and the necessity for reseeding.
Due to concerns about accelerated soil erosion in the in the Nansemond, an erosion and sediment evaluation was conducted in 1985. As a consequence of the evaluation findings, RCWP critical areas were expanded to include areas of high erosion (the new boundary included a one-mile radius from all tributaries).
In treating the expanded critical area, the project established a priority checklist for ranking. Weights were based primarily on distance to live streams and less than optimal soil or animal waste management. Animal waste operations were given twice the priority of croplands, and erosion problems were given the same priority as pesticide and fertilizer management problems. Farms with animal operations and no cropland treatment needs did not qualify.
Unfortunately, the project was not able to secure the additional funds necessary to treat all farms needing and wanting BMPs in the expanded critical areas.
BMPs Utilized in the Project * Units Goals Achievements Total % Permanent vegetative cover (BMP 1) acres 200 282 141 Animal waste management system (BMP 2) # 41 22 54 Diversion system (BMP 5) feet 15,000 7,750 52 Grazing land protection system (BMP 6) # 30 21 70 Waterway system (BMP 7) acres 20 11 55 Cropland protection system (BMP 8) acres 14,000 9,452 68 Conservation tillage system (BMP 9) acres 9,500 7,870 83 Stream protection system (BMP 10) feet 12,000 8,000 67 Permanent vegetative cover on critical areas (BMP 11) acres 100 66 66 Sediment retention, erosion or water control structures (BMP 12) # 100 109 109 Tree planting (BMP 14) acres 100 0 0 Fertilizer management (BMP 15) acres 14,000 14,536 104 Pesticide management (BMP 16) acres 14,000 14,530 104*Please refer to Appendix I for description/purpose of BMPs.
Pollutant Critical Area Goals Source Units Total % Implemented Total % Implemented Cropland acres 23,908 63% 16,665 90% Dairies # 1 100% 1 100% Feedlots # 50 74% 38 97% Poultry # 8 38% 6 50% Contracts # 184 58% 107 81%
Specific goals for each phase in the work plan included:
Setting pre-RCWP baseline as a basis for comparison
Collecting water quality data during the project so that annual changes could be observed
Conducting an intensive water quality survey at the end of the program
Estuarine Monitoring: 1983 - 1991
Estuarine Monitoring: 4 stations in Nansemond River estuary and 3 stations in Chuckatuck Creek estuary
Estuarine Monitoring: DO, salinity, TSS, nitrate nitrogen (NO3-N), dissolved orthophosphate (OP), FC, BOD
STORET STORET AGENCY CODES STATION NO. Chuckatuck Creek 21VASWCB 2-CKT000.19 2-CKT001.63 2-CKT003.05 Nansemond River 21VASWCB 2-NAN000.20 2-NAN005.82 2-NAN007.89 2-NAN012.53 2-NAN019.14
The project did not unequivocally meet its objectives for reducing fecal coliform, total soil loss, turbidity and sediment loading, plant nutrients, and pesticides. Some of the measurements needed for determination of goal achievement were never made, such as pesticide concentrations and total soil loss. Analysis of the water supply lakes in the project area indicated high variability in water quality data and little evidence of trends. For the other variables, initial trend analysis in the Nansemond River estuary indicated that TSS and NO3-N appear to be declining, but OP is increasing. NO3-N and OP are declining in the Chuckatuck Creek estuary. These trends may be attributable to changes in point source discharges on Nansemond River and closure of a large swine operation on Chuckatuck Creek rather than BMPs installed through the RCWP project.
Nansemond-Chuckatuck RCWP Project. 1992. Ten-Year Report.
Smolen, M.D., S.L. Brichford, J. Spooner, A. Lanier, T.B. Bennett, S.W. Coffey, and K.J. Adler. 1989. NWQEP 1988 Annual Report: Status of Agricultural Nonpoint Source Projects. EPA 506/9-89/002.
Spooner, J., J.A. Gale, S.L. Brichford, S.W. Coffey, A.L. Lanier, M.D. Smolen, and F.J. Humenik. 1991. NWQEP Report: Water Quality Monitoring Report for Agricultural Nonpoint Source Projects - Methods and Findings from the Rural Clean Water Program. National Water Quality Evaluation Project, NCSU Water Quality Group, Biological and Agricultural Engineering Department, North Carolina State University, Raleigh, NC.